Section 6 - INSPECTION, TESTING AND
DOCUMENTATION
6.1 INSPECTION OF WORK
- 6.1.1 GENERAL
Telecommunications Center or
its designees shall have access to construction sites.
To enable Telecommunications Center to inspect
telecommunications facilities work, the contractor must:
- Provide a progress schedule with the installation of
telephone raceways and spaces shown as a separate item.
- Immediately notify Telecommunications Center of any change
in architectural drawings and/or plans affecting
telecommunications.
- Provide proper access to facilities for inspections.
- Notify Telecommunications Center when any work is ready for
inspection.
NOTE: All underground work must be inspected and approved by
Telecommunications Center before the site is covered with dirt or
concrete. Failure to have the work inspected shall result in uncovering
the area at the contractor's expense.
6.2 TESTING
- 6.2.1 GENERAL
The contractor shall submit to
Telecommunications Center, a detailed test procedure to be used
for every project. All cables shall be tested for length,
attenuation, impedance, grounds, shorts, reversals, and continuity
of communications conductors and shields. See Section 10. for
testing requirements for fiber optic cable. Upon
completion, test results shall be submitted to Telecommunications
Center for final approval and acceptance and made part of the
document. The contractor shall guarantee 100 percent continuity on
all conductors on all cables. Telecommunications Center
will perform verification testing it deems necessary before
accepting a job. Failure during testing will result in re-pulling
cables at the contractor expense.
- 6.2.2 STATION CABLES
All category 6 station
cable shall be tested to category 6 standards. Station cables that
do no pass the test will be repaired or replaced by the contractor
at no additional cost and re-tested to meet the required
specifications. Telecommunications Center recommends using a Fluke
DTX-1200 CAT 6 tester for testing the cable or equivalent. The
contractor will provide to Telecommunications Center documented
readable test results for all stations. The format will comply
with Telecommunications Center Documentation Standards.
Station cable tests shall be performed to manufacturer's
specifications and Telecommunications Center standards. Riser cable
tests shall be performed to manufacturer's specifications and
Telecommunications Center standards. Trunk cable tests shall be performed
to manufacturer's specifications and Telecommunications Center standards.
Test results shall be email to the Facilities Planning Department and the
Project Manager for the Telecommunications Center.
6.3 DOCUMENTATION STANDARDS
- 6.3.1 CONTRACTOR DOCUMENTATION REQUIREMENTS
Cable records during installation and complete sets of cable records are
required at project completion. Labeling of all termination hardware and
cabinets with information provided by Telecommunications Center. A complete
set of as-built drawings upon completion of the project, both on marked up
blueprints and in AutoCAD type (e.g., DXF format on 3.5" diskettes).
Telecommunications Center will specify the version/release number of AutoCAD
acceptable at the time of the project award. OTDR test results to manufacturer's
specifications and Telecommunications Center standards for all fiber optic cable
installed. The documentation must include OTDR readings, fiber route diagrams and
end-to-end attenuation results for multimode and singlemode fiber cable. All fiber
OTDR readings shall be made bi-directionally on all fiber cable.
Station cable tests shall be performed to manufacturer's specifications and
Telecommunications Center standards. Riser cable tests shall be performed to
manufacturer's specifications and Telecommunications Center standards. Trunk
cable tests shall be performed to manufacturer's specifications and Telecommunications
Center standards. Test results shall be email to the Facilities Planning Department
and the Project Manager for the Telecommunications Center.
- 6.3.2 Telecommunications Center PROVIDED DOCUMENTATION
Contract drawings for the project. Labeling
information for termination equipment.
|